How to install an automatic bollard

This article mainly introduces the installation of automatic bollards. Also known as automatic rising bollards, these devices effectively manage vehicle access to secure traffic order and the safety of key facilities and areas. After years of development, automatic bollards can be categorized into fully automatic, semi-automatic, removable, and fixed types.

Their protective capabilities meet the needs of civilian security and are suitable for high-traffic areas such as campuses, scenic spots, stations, high-speed railway stations, government buildings, hospitals, shopping malls, pedestrian streets, and other important locations.

Installation Diagram

Installation Diagram

Preparation of Materials and Equipment Before Installation

Materials and Equipment Preparation

Construction Standards for Bollard Installation

Excavation of the Foundation Trench

The foundation trench should have a depth of 1.5 meters, a width of 1 meter, and a length equal to the total center-to-center distance of all bollards, plus an additional meter.

Excavation of Foundation Trench

Construction of a Water Retention Pit at Road Intersection

A water retention pit with a 600 mm corrugated pipe, 1.8 meters deep, should be installed. Inside the pit, an automatic pump with a float switch should be used for water drainage.

Removal of Road Surface

For cement, asphalt, or other hard road surfaces, first use a saw to cut along the edges of the foundation trench. Then use electric hammers or other tools to remove the surface layer, preparing the area for the restoration of the road surface.

Foundation Trench Requirements and Drainage Layer Setup

The foundation trench should have vertical walls and a smooth, level base. After excavation, fill the bottom with 3-5 cm gravel to create a drainage layer, 20 cm thick. Then, add a 20 cm layer of fine sand, ensuring uniform thickness across all layers to prepare for placing the pre-buried bollard casing.

Foundation Trench and Drainage Layer Setup

Bollard Installation Steps

Installation of Pre-buried Components

Pre-buried Component Installation

Laying Conduit and Wiring

Conduit and Wiring Installation

Reinforcing the Pre-buried Casing with Steel Bars

Reinforcing Pre-buried Casing

Wiring Process

Backfilling and Concrete Pouring

Once the reinforcement is securely welded, and the grounding is completed, backfill with 20 cm of soil, compacting it to prevent concrete from seeping into the drainage layer. Pour concrete to a height of 10 cm below the road surface to leave space for restoring the original surface.

Backfilling and Pouring Concrete

Device Debugging

After the installation, adjust the guiding rods to ensure the bollard’s alignment with the surface panel, checking that the bollard rises and falls smoothly without any stalling.

Device Debugging

Road Surface Restoration and Site Cleaning

When restoring the original road surface, ensure that it is level with the device’s upper panel. After completing the surface restoration, place barriers and signs. Wait until the concrete on the road and underground has fully set before using the device. Note: Avoid allowing heavy vehicles to pass for 7 days after the installation.

Contact Us Let’s start collaborating

You can always trust WuiiTeco®